Home » Posts tagged 'kiran morzaria'
Tag Archives: kiran morzaria
Cadence Minerals #KDNC – Amapá Iron Ore Project Licensing on Schedule. Project Financing Discussions Advancing.
Cadence Minerals (AIM: KDNC) is pleased to report the progress of the environmental licensing and the testing of the 67% ‘Green Iron’ processing flow sheet at the Amapá Iron Ore Project.
Highlights:
- Installation Licences for the Amapá mine and railway remain on schedule to be granted this year.
- The license application for the port was submitted in September and is also scheduled for a grant this year.
- The test work for sixty-seven per cent (67%) iron flow sheet is due for completion in the fourth quarter of this year.
- The Project is actively discussing the equity portion of project financing to complement the existing debt financing MOU.
Kiran Morzaria, the CEO of Cadence, commented, “It’s great to see the continued progress at Amapá. The Project has consistently delivered all the required environmental studies and applications either on time or ahead of schedule. Based on the positive feedback from the local government, we understand that all necessary permits will be granted before the year’s end. Additionally, we are actively advancing the development of a 67% “green iron” product and securing equity financing for the Project.”
Licensing
As announced in September 2023 (News Release Here), the Amapá Project has agreed with the Amapá State Environmental Agency (“SEMA”) to an expedited environmental licensing process, given the Project was previously operating and had been granted all required licenses.
The Amapá Project owns the required Mining Concessions; however, it must obtain a Mine Extraction and Processing Permit (“Mining Permit”) to begin operation. To obtain this permit, the Amapá Project must obtain an Installation License (“LI”) to begin construction and, when constructed, an Operational License (“LO”). An LI and LO are also required to construct and operate the railway and port.
In April 2023, the Amapá Project submitted the required environmental studies and applications for the Amapá mine and railway. This application was in the form of the Environmental Control Plan, “PCA” (Plano de Controle Ambiental), and an Environmental Control Report, “RCA” (Relatório de Controle Ambiental).
In early September, the Amapá Project submitted the required environmental studies and application for the LI grant for iron ore port. This application was submitted after those for the mine and railway as SEMA required an extended environmental study. Nevertheless, the application was submitted on schedule.
Our joint venture has continued engaging with SEMA and other relevant authorities, who have indicated that the LI for the rail and mine remain on schedule for the grant this year. Given the impact that the railway’s restart will make on local communities, the installation license for the railway is anticipated to have some conditions precedent. This is expected in any project of this nature. The Amapá project management team always anticipated this as part of the required licensing requirements to redevelop the Amapá Iron Ore project.
Our understanding from SEMA is that, based on the current timeline, all the LIs will be granted by the end of 2024.
67% ‘Green Iron’ Flowsheet
The testing of the 67% processing route is continuing. The Amapá Project originally produced three products: 58%, 62%, and 65% iron ore concentrate. The 2023 pre-feasibility improved this product mix, with only a 62% and 65% produce mix being envisaged. The current flowsheet aims to produce one hundred per cent 67% iron ore concentrate, which has both a premium in price and is anticipated to be a growth market in the iron ore concentrate as it represents the feedstock to DRI furnaces. These furnaces enable the decarbonising of the steel industry by replacing blast furnaces.
The main variances in the proposed 67% flow sheet involve:
- Removing the jigging circuit, with the iron being recovered via the grinding, magnetic, and flotation circuits. This will improve the iron recovery rate.
- Replacing hydrocyclone desliming with thickeners, improving classification efficiency and lowering power consumption.
- The 67% flow sheet will remove the 62% product stream, eliminating the spiral circuit. This will shorten the process flow and reduce power consumption.
- Adding a flowsheet to improve iron concentrates from 65.4% to 67% via regrinding the material from the magnetic separator, meaning finer particles can be further liberated, improving iron concentrate grade to 67%.
- Replacement of all slurry, water, and reagent pumps involved in the beneficiation process.
- A concentrate slurry pipeline and filtrate water return pipeline system will be built to replace truck transportation.
- The particle size of the concentrate after the tower mills is too fine to be filtered by the existing vacuum disc filters. Therefore, horizontal press filters are required to ensure the moisture content of the filter cake is no larger than 8%.
- A train loading system will be built in the train loading area.
A summary of the new flow sheet is available here.
The main metallurgical test work being carried out includes raw ore liberation testing, desliming testing, magnetic separation testing, floatation testing, grinding work index testing, concentrate tailings thickening testing and tailings filtration testing. We expect this work to be completed in the fourth quarter of this year.
Project Financing
In October 2023 (News Release Here), our joint venture company and DEV Mineração S.A. (“DEV”) entered into a memorandum of understanding (“MOU”). The MOU is in place to secure the required project debt financing for the construction and re-development of the Amapá Project.
To complement the project debt financing, our joint venture is actively engaging with several potential financing partners to provide the equity portion of the funding at the project level.
About the Amapá Project and Cadence Ownership
The Amapá Project is a brownfield integrated iron ore project in the Amapá State of Brazil. It has Mineral Resources of 276 million tonnes (Mt) at 38.33% Iron (Fe) and Ore Reserves of 196 Mt at 39.34%. The Project consists of the mine, processing plant, wholly owned port and a 194km railway, all operated by PBA.
As of August 31st, 2024, Cadence’s total investment in the Amapá million was approximately US$14.2 million, and its equity stake in the project stands at 34.5%, an increase of approximately US$0.57 million since 30 June 2024.
For further information contact:
|
|
Cadence Minerals plc | +44 (0) 20 3582 6636 |
Andrew Suckling | |
Kiran Morzaria | |
Zeus Capital Limited (NOMAD & Broker) | +44 (0) 20 3829 5000 |
James Joyce | |
Darshan Patel
Isaac Hooper |
|
Fortified Securities – Joint Broker | +44 (0) 20 3411 7773 |
Guy Wheatley | |
Brand Communications | +44 (0) 7976 431608 |
Public & Investor Relations | |
Alan Green |
Qualified Person
Kiran Morzaria B.Eng. (ACSM), MBA, has reviewed and approved the information contained in this announcement. Kiran holds a Bachelor of Engineering (Industrial Geology) from the Camborne School of Mines and an MBA (Finance) from CASS Business School.
Cautionary and Forward-Looking Statements
Certain statements in this announcement are or may be considered forward-looking. Forward-looking statements are identified by their use of terms and phrases such as “believe”, “could”, “should”, “envisage”, “estimate”, “intend”, “may”, “plan”, “will”, or the negative of those variations or comparable expressions including references to assumptions. These forward-looking statements are not based on historical facts but rather on the Directors’ current expectations and assumptions regarding the company’s future growth results of operations performance, future capital, and other expenditures (including the amount, nature, and sources of funding thereof) competitive advantages business prospects and opportunities. Such forward-looking statements reflect the Directors’ current beliefs and assumptions and are based on information currently available to the Directors. Many factors could cause actual results to differ materially from the results discussed in the forward-looking statements, including risks associated with vulnerability to general economic and business conditions, competition, environmental and other regulatory changes actions by governmental authorities, the availability of capital markets reliance on crucial personnel uninsured and underinsured losses and other factors many of which are beyond the control of the company. Although any forward-looking statements contained in this announcement are based upon what the Directors believe to be reasonable assumptions. The company cannot assure investors that results will be consistent with such forward-looking statements.
The company deems the information contained within this announcement to constitute Inside Information as stipulated under the Market Abuse Regulation (E.U.) No. 596/2014, as it forms part of U.K. domestic law under the European Union (Withdrawal) Act 2018, as amended. Upon the publication of this announcement via a regulatory information service, this information is considered to be in the public domain.
Cadence Minerals #KDNC – Fundraise to raise £750,000 for further Amapa Project activities
Cadence Minerals (AIM: KDNC) announces that it has successfully raised, subject to Admission, £625,000 before expenses (the “Placing”) by the way of a placing arranged by Fortified Securities of 25,000,000 new ordinary shares (the “New Ordinary Shares”) in the capital of the Company at a price of 2.5 pence per Ordinary Share (the “Issue Price”).
In addition to the above subscription, Andrew Suckling, Kiran Morzaria, and Donald Strang (together, the “Subscriber Directors”) have also agreed to subscribe for an aggregate of 5,000,000 New Ordinary Shares at the Issue Price, raising gross proceeds of £125,000 (“Subscription”).
The Issue Price represents a discount of approximately 18 per cent to the closing price of 3.05 pence per ordinary share on 11 July 2024, being the latest practicable business day prior to the publication of this Announcement.
Use of Funds
The net proceeds of the fundraise will be used to fund Cadence’s investment in the Amapá Iron Ore Project in Brazil (“Amapá”, “Project” or “Amapá Project”), specifically:
- The continued testing of the 67% Fe “Green Iron” product flow sheet, to a PFS level or accuracy.
- Prepare and publish a revised PFS economic model should the 67% flow sheet be successful that reflects the increase pricing anticipated from the product and any change in capital or operating expenditure in the revised flowsheet.
- General working capital at the Amapá Project and ongoing funding for the licensing for the tailing storage facility.
Related Party Transactions
As the Directors of the Company, being the Subscribing Directors, are considered to be “related parties” as defined under the AIM Rules, their participation in the Subscription constitutes a related party transaction for the purposes of Rule 13 of the AIM Rules.
Director | Subscription Amount | No. of New Ordinary Shares subscribed for | Resulting shareholding in the Company | % shareholding in the Company’s issued share capital as enlarged by the Placing |
Andrew Suckling
(Non-Executive Chair) |
£40,000 | 1,600,000 | 1,981,602 | 0.87% |
Kiran Morzaria
(Chief Executive Officer) |
£45,000 | 1,800,000 | 3,373,240 | 1.48% |
Donald Strang
(Finance Director) |
£40,000 | 1,600,000 | 2,557,545 | 1.12% |
Adrian Fairbourn
(Non-Executive Director) |
Nil | Nil | 731,005 | 0.32% |
Total | £125,000 | 5,000,000 | 8,643,392 | 3.79% |
Adrian Fairbourn, being a Director of the Company independent of the fundraise, having consulted with Cadence Mineral’s Nominated Adviser, WH Ireland Limited, consider the terms of the fundraise to be fair and reasonable insofar as the Company’s shareholders are concerned.
Application will be made for the admission to trading on the AIM market (“AIM”) of London Stock Exchange plc (“LSE”) for the New Ordinary Shares (“Admission”). Admission is expected to occur at 8.00 a.m. on or around 19 July 2024. The New Ordinary Shares will represent approximately 13.2 per cent. of the Company’s issued share capital immediately following Admission.
Following Admission, the Company’s issued and fully paid share capital will consist of 227,637,704 Ordinary Shares, all of which carry one voting right per share. The Company does not hold any Ordinary Shares in treasury. The figure of 227,637,704 Ordinary Shares may be used by shareholders as the denominator for the calculation by which they will determine if they are required to notify their interest in, or a change to their interest in, the share capital of the Company under the Disclosure Guidance and Transparency Rules of the Financial Conduct Authority.
The New Ordinary Shares will be issued fully paid and will rank pari passu in all respects with the Company’s existing Ordinary Shares.
For further information contact:
|
|
Cadence Minerals plc | +44 (0) 20 3582 6636 |
Andrew Suckling | |
Kiran Morzaria | |
WH Ireland Limited (NOMAD & Broker) | +44 (0) 20 7220 1666 |
James Joyce | |
Darshan Patel
Isaac Hooper |
|
Fortified Securities – Joint Broker | +44 (0) 20 3411 7773 |
Guy Wheatley | |
Brand Communications | +44 (0) 7976 431608 |
Public & Investor Relations | |
Alan Green |
In accordance with Article 19 of the UK Market Abuse Regulation, detailed information is set out below.
1 | Details of the person discharging managerial responsibilities/person closely associated | ||||
a) | Name: | Andrew Suckling | |||
2 | Reason for the notification | ||||
a) | Position/Status: | Non-Executive Chair | |||
b) | Initial Notification/Amendment: | Initial Notification | |||
3 | Details of the issuer, emission allowance market participation, auction platform, auctioneer or auction monitor | ||||
a) | Name: | Cadence Minerals plc | |||
b) | LEI: |
|
|||
4. | Details of transaction(s); section to be repeated for (i) each type of instrument; (ii) each type of transaction; (iii) each date; and (iv) each place where transactions have been conducted. | ||||
a) | Description of the financial instrument:
Identification code: |
Ordinary shares of £0.01
ISIN: GB00BJP0B151 |
|||
b) | Nature of the transaction: | Purchase of Shares | |||
c) | Price(s) and volume(s): | Price(s) | Volume(s) | ||
2.5p | 1,600,000 | ||||
d) | Aggregated volume:
Price: |
1,600,000
£40,000 |
|||
e) | Date of the Transaction: | 11 July 2024 | |||
f) | Place of the Transaction: | London Stock Exchange |
1 | Details of the person discharging managerial responsibilities/person closely associated | ||||
a) | Name: | Kiran Morzaria | |||
2 | Reason for the notification | ||||
a) | Position/Status: | Chief Executive Officer | |||
b) | Initial Notification/Amendment: | Initial Notification | |||
3 | Details of the issuer, emission allowance market participation, auction platform, auctioneer or auction monitor | ||||
a) | Name: | Cadence Minerals plc | |||
b) | LEI: |
|
|||
4. | Details of transaction(s); section to be repeated for (i) each type of instrument; (ii) each type of transaction; (iii) each date; and (iv) each place where transactions have been conducted. | ||||
a) | Description of the financial instrument:
Identification code: |
Ordinary shares of £0.01
ISIN: GB00BJP0B151 |
|||
b) | Nature of the transaction: | Purchase of Shares | |||
c) | Price(s) and volume(s): | Price(s) | Volume(s) | ||
2.5p | 1,800,000 | ||||
d) | Aggregated volume:
Price: |
1,800,000
£45,000 |
|||
e) | Date of the Transaction: | 11 July 2024 | |||
f) | Place of the Transaction: | London Stock Exchange |
1 | Details of the person discharging managerial responsibilities/person closely associated | ||||
a) | Name: | Donald Strang | |||
2 | Reason for the notification | ||||
a) | Position/Status: | Finance Director | |||
b) | Initial Notification/Amendment: | Initial Notification | |||
3 | Details of the issuer, emission allowance market participation, auction platform, auctioneer or auction monitor | ||||
a) | Name: | Cadence Minerals plc | |||
b) | LEI: |
|
|||
4. | Details of transaction(s); section to be repeated for (i) each type of instrument; (ii) each type of transaction; (iii) each date; and (iv) each place where transactions have been conducted. | ||||
a) | Description of the financial instrument:
Identification code: |
Ordinary shares of £0.01
ISIN: GB00BJP0B151 |
|||
b) | Nature of the transaction: | Purchase of Shares | |||
c) | Price(s) and volume(s): | Price(s) | Volume(s) | ||
2.5p | 1,600,000 | ||||
d) | Aggregated volume:
Price: |
1,600,000
£40,000 |
|||
e) | Date of the Transaction: | 11 July 2024 | |||
f) | Place of the Transaction: | London Stock Exchange |
Cadence Minerals #KDNC – Updated PFS Level Economic Study Delivers an Increased Net Present Value of US$1.145 Billion
Cadence Minerals (AIM: KDNC) is pleased to announce the results from the updated economic study, the progress on the environmental applications and the ongoing development of the 67% ‘Green Iron’ processing flow sheet at the Amapá Ore Project (“Amapá”, “Project” or “Amapá Project”). Since the end of March 2024, Cadence’s total investment in the Amapá Project had increased by approximately US$0.7 million to approximately US$13.9 million, and consequently, the equity stake in the project now stands at 34.2%.
Highlights:
- 20% increase of Post-tax Net Present Value (“NPV”) to US$1.14 billion at a discount rate of 10%, with profit after tax of US$3.14 billion over the Life of Mine (“LOM”).
- 10% increase in average production after ramp-up to 5.82 million dry metric tonnes (“DMT”) per annum (“Mtpa”) of Fe concentrate, consisting of 4.81 Mtpa at 65.4% Fe and 1.01 Mtpa at 62% Fe concentrate.
- A 6% decrease in Free on Board (“FOB”) C1 Cash Costs to US$33.5/dmt at the port of Santana. Cost and Freight (“CFR”) C1 Cash Costs US$62.2/dmt in China.
- Improved Post-tax Internal Rate of Return from 34% to 42%.
- The port’s environmental licensing is on schedule with the studies complete and the required reports being drafted, it is due to be submitted on schedule in the current quarter of this year.
- Testing of the 67% Fe “Green Iron” flow sheet has commenced, and results are expected by the end of September 2024.
- If successful, the 67% flow could increase the net operating profit of the Project, at full production, from approximately US$227 million to US$324 million per year.
Cadence CEO, Kiran Morzaria, commented: “On behalf of our Board, I am thrilled with the positive outcomes from the updated economic study at the Amapá Ore Project, along with further significant progress made at Amapá. The increased net present value of US$1.145 billion and the enhanced post-tax internal rate of return demonstrate substantial improvements to the Project’s already robust economics.
The ongoing development of the 67% ‘Green Iron’ processing flow sheet and the Project’s 100% renewable power source exemplify our commitment to propelling Amapa forward to meet the growing demand for low-carbon iron ore and steel, while at the same time demonstrating a potential 43% uplift in projected annual net operating profit.
We are optimistic about the potential of the Amapá Iron Ore Project and look forward to providing further updates on our progress in the future.”
Updated PFS-level economic study
In March this year, the Amapa Project announced the results of the optimisation study, which delivered material capital savings to the Project. Based on these results, the Amapa Project carried out an updated PFS-level economic study.
Updated Mining Schedule
As part of the optimisation study completed in March 2024, the engineering consultants identified higher availability at the processing plant, which increased the annual run-of-mine feed rate to the processing plant. As a result of this, it was necessary to re-examine the mining and other related engineering disciplines, and in particular, the mine schedule had to be recalculated to optimise the project’s NPV.
A life of mine production plan was scheduled using the Deswik.Blend® Scheduler Optimizer. The solids used in the mine scheduling were based on the final pit design, with an SMU (Selective Mining Unit) of 100 m x 200 m x 4 m. The life of mine schedule allows for 15 years of production with the current economic values and cut-off of 25% Fe. The resultant life of mine strip ratio is approximately 0.4:1 (tonnes waste: tonnes ore) and an average ore mine delivered to the plant of 13 million metric tonnes per annum.
Project Financial Analysis
An updated PFS financial model, which included the updated mining schedule, lower capex, and lower operational costs, was developed to evaluate the project’s economics. All other aspects of the financial analysis remained the same as per the PFS published in January 2023, including the iron ore concentrate price. Which was a long-term average price for 62% iron ore concentrate of US$95/dmt and US$118.8/dmt for 65.4% iron ore concentrate, both quoted on a Cost and Freight (“CFR”) basis. As of 8 July 2024 the 62% iron ore concentrate price was US$108.75/dmt and 65% iron ore fines was US$129/dmt. Summary results from the financial model outputs are presented in the tables below, including financial analysis. The financial model considers 100% equity funding for the Project, although, in reality, the financing of the Project will be a mix of debt and equity. However, the existing obligations in terms of principal repayment and current interest liabilities payable have been included in the financial model. A summary of the key financial information is presented below, alongside the 2022 PFS data.
Table 1.1 Key Project Metrics (100% project basis)
Metric | Unit | 2022 PFS Data | 2024 PFS Data |
Total ore feed to the plant | Mt (dry) | 176.88 | 176.93 |
Life of Mine | Years | 16 | 15 |
Fe grade of ore feed to the plant | % | 39.34 | 39.34 |
Recovery | % | 76.27 | 76.27 |
62.0% iron ore concentrate production | Mtpa | 0.89 | 0.95 |
65.4% iron ore concentrate production | Mtpa | 4.23 | 4.51 |
C1 Cash Costs FOB * | US$/dmt | 35.53 | 33.50 |
C1 Cash Costs CFR ** | US$/dmt | 64.23 | 52.20 |
Pre-Production capital investment*** | US$M | 399 | 343 |
Sustaining capital investment over LOM**** | US$M | 245 | 245 |
Post-tax NPV (10%) | US$M | 949 | 1,145 |
Post-tax IRR | % | 34 | 42 |
Project payback | Years | 4 | 4 |
Total profit after tax (net operating profit) | US$B | 2.96 | 3.14 |
* | Means operating cash costs, including mining, processing, geology, OHSE, rail, port and site G&A, divided by the tonnes of iron ore concentrate produced. It excludes royalties and is quoted on a FOB basis (excluding shipping to the customer). |
** | Means the same as C1 Cash Costs FOB; however, it includes shipping to the customer in China (CFR). |
*** | Includes direct tax credit rebate over 48 months |
**** | Includes both sustaining CAPEX and deferred capital expenditure, specifically, improvements to the railway and the installation of conveyor belt and mine site to rail load out |
Table 1.2 FOB and CFR average cash cost per tonne of dry product over the LOM
Cash Cost Per Discipline | PFS 2022 | PFS 2024 |
US$/dmt | US$/dmt | |
Mine | 17.05 | 16.73 |
TSF | 0.08 | 0.08 |
Beneficiation Plant, Road / Conveyor Transfer & Rail Loading | 12.43 | 10.94 |
Rail Freight | 2.43 | 2.43 |
Port | 1.55 | 1.55 |
G & A (5% total cost) | 1.99 | 1.77 |
FOB Cash Costs | 35.53 | 33.50 |
Marine Logistics | 28.70 | 28.70 |
CFR Cash Costs | 64.23 | 62.20 |
Table 1.3 Summary of key financial information for the Project.
Item Over Life of Mine | Unit | 2022 PFS Data | 2024 PFS Data |
Gross revenue | US$M | 9,387 | 9,389 |
Freight (Maine Logistics) | US$M | (2,350) | (2,351) |
Net Revenue | US$M | 7,037 | 7,038 |
Operating costs | US$M | (2,910) | (2,744) |
Royalties and taxes (excluding income tax) | US$M | (373) | (373) |
EBITDA | US$M | 3,754 | 3,922 |
EBIT | US$M | 3,315 | 3,547 |
Net Taxes and Interest | US$M | (355) | (390) |
Net Operating Profit | US$M | 2,960 | 3,144 |
Initial, Sustaining capital costs & repayments | US$M | (727) | (645) |
Free Cash Flow | US$M | 2,672 | 2,874 |
Item | Unit | 2022 PFS Data | 2024 PFS Data |
LOM | Years | 16 | 15 |
Discount rate | % | 10 | 10 |
NPV | US$M | 949 | 1,145 |
IRR | % | 34 | 42 |
Project Payback | Years | 4 | 4 |
Licensing
As announced in September 2023, Amapá Project Management had agreed with the Amapá State Environmental Agency (“SEMA”) to an expedited environmental process, given the Project had previously been granted all its Operational Licenses (“LO”).
SEMA is reviewing the application for the Installation License (“LI”) for the mine and railway, which were submitted in March 2024. The the LI application for the wholly-owned port are nearing completion, with the final reports due for submission in the current quarter. Our understanding from SEMA is that based on the current timeline, the LI will be granted by the end of 2024. The LI allows the rehabilitation and construction of the Amapá Project, and once this is completed, the LO is granted, and mining operations can commence.
67% ‘Green Iron’ Flowsheet
The Amapá Project Management team continues to develop the ‘green iron’ flowsheet. Part of the work entails carrying out a mineralogical and multi-elemental analysis of run-of-mine ore, concentrate, and tailings and testing the full circuit at a pilot-scale level.
To this end, the Project has completed a life-of-mine sampling programme, collecting approximately two tonnes of material, which was shipped to our independent consultant engineers in March. The samples were shipped and cleared Chinese customs in late June. The samples have been checked and reconciled, and flow sheet testing results are expected by the end of the current quarter.
Assuming the testing confirms the flow sheet, we will update the project economics to reflect the increased revenue and any capital expenditure changes and update the market with these figures.
Project Financing
In October 2023, Cadence announced a memorandum of understanding (“MOU”) to obtain debt financing for the Project. More information can be found in the announcement here. The MOU remains in place and our primary focus has been on securing the equity needed for the Project’s construction.
We have signed several non-disclosure agreements in this regard, and interested parties have been and will be conducting technical site visits as part of their due diligence. The Project will need to have the necessary equity and debt in place to start construction. We will inform the markets if any definite agreements are made. In the meantime, Cadence plans to fund ongoing work, including the advancement of the 67% flow sheet, licensing, maintenance of the tailings storage facility, and general working capital for the Project.
About the Amapá Project and Cadence Ownership
The Amapá Project is a brownfield integrated iron ore project in the Amapá State of Brazil. It has Mineral Resources of 276 million tonnes (Mt) at 38.33% Iron (Fe) and Ore Reserves of 196 Mt at 39.34%. The Project comprises the mine, processing plant, wholly owned port and a 194km railway.
Since the end of March 2024, Cadence’s total investment in the Amapá Project had increased by approximately US$0.7 million to approximately US$13.9 million, and consequently, the equity stake in the project now stands at 34.2%.
For further information contact:
|
|
Cadence Minerals plc | +44 (0) 20 3582 6636 |
Andrew Suckling | |
Kiran Morzaria | |
WH Ireland Limited (NOMAD & Broker) | +44 (0) 20 7220 1666 |
James Joyce | |
Darshan Patel
Isaac Hooper |
|
Fortified Securities – Joint Broker | +44 (0) 20 3411 7773 |
Guy Wheatley | |
Brand Communications | +44 (0) 7976 431608 |
Public & Investor Relations | |
Alan Green |
Qualified Person
Kiran Morzaria B.Eng. (ACSM), MBA, has reviewed and approved the information contained in this announcement. Kiran holds a Bachelor of Engineering (Industrial Geology) from the Camborne School of Mines and an MBA (Finance) from CASS Business School.
Cautionary and Forward-Looking Statements
Certain statements in this announcement are or may be considered forward-looking. Forward-looking statements are identified by their use of terms and phrases such as “believe”, “could”, “should”, “envisage”, “estimate”, “intend”, “may”, “plan”, “will”, or the negative of those variations or comparable expressions including references to assumptions. These forward-looking statements are not based on historical facts but rather on the Directors’ current expectations and assumptions regarding the company’s future growth results of operations performance, future capital, and other expenditures (including the amount, nature, and sources of funding thereof) competitive advantages business prospects and opportunities. Such forward-looking statements reflect the Directors’ current beliefs and assumptions and are based on information currently available to the Directors. Many factors could cause actual results to differ materially from the results discussed in the forward-looking statements, including risks associated with vulnerability to general economic and business conditions, competition, environmental and other regulatory changes actions by governmental authorities, the availability of capital markets reliance on crucial personnel uninsured and underinsured losses and other factors many of which are beyond the control of the company. Although any forward-looking statements contained in this announcement are based upon what the Directors believe to be reasonable assumptions. The company cannot assure investors that results will be consistent with such forward-looking statements.
Cadence Minerals #KDNC – Further Progress at the Amapa Iron Ore Project
Cadence Minerals (AIM: KDNC) is pleased to announce an increase in the rate of progress on the environmental applications and the ongoing development of the 67% ‘Green Iron’ processing flow sheet at the Amapá Ore Project (“Amapá”, “Project” or “Amapá Project”).
Highlights:
- Submission of the Environmental Control Plan – “PCA” (Plano de Controle Ambiental) and an Environmental Control Report – “RCA” (Relatório de Controle Ambiental) submitted ahead of schedule for the Mine and Railway.
- The PCA and RCA are part of the state environmental approval process required to obtain an Installation License (“LI”), which, once granted, allows construction at Amapá to commence.
- The port’s environmental licensing is on schedule with the PCA and RCA and is due to be submitted in the third quarter of this year.
- Sampling of two tonnes of iron ore representing the life of mine material is complete. This will be sent to an engineering firm in China to test the 67% Fe ”Green Iron” flow sheet.
Cadence CEO Kiran Morzaria commented: “The Cadence Board and Management team are thrilled with the recent uptick in the pace of developments at the Amapá Iron Ore Project. The early submission of our environmental reports underscores the Project’s commitment to sustainability and efficient project management, and this along with the anticipated approval of our installation license for the current year, is paving the way for the rehabilitation and commissioning of the Amapá Project. Our dedication to the ‘Green Iron’ initiative reflects our vision for an environmentally lower carbon iron ore product. I look forward to reporting further progress to you in the coming weeks and months.”
Licensing
As announced in September 2023, Amapá Project Management had agreed with the Amapá State Environmental Agency (“SEMA”) to an expedited environmental process, given the Project had previously been granted all its Operational Licenses (“LO”).
The PCA and RCA for the mine and railway were submitted to SEMA last week. SEMA will now review the application. The RCA and PCA for the wholly-owned port continue progressing, with the final reports due for submission in the third quarter of this year. Our understanding from SEMA is that based on the current timeline, the LI will be granted by the end of 2024. The LI allows the rehabilitation and construction of the Amapá Project, and once this is completed, the LO is granted, and mining operations can commence.
67% ‘Green Iron’ Flowsheet
The Amapá Project Management team continue to develop the ‘green iron’ flowsheet. Part of the work entails carrying out a mineralogical and multi-elemental analysis of run-of-mine ore, concentrate, and tailings, along with testing the full circuit at a pilot-scale level. To this end, the Project has completed a life-of-mine sampling, collecting approximately two tonnes of material, which will now be shipped to our independent processing engineers in China.
About the Amapá Project and Cadence Ownership
The Amapá Project is a brownfield integrated iron ore project in the Amapá State of Brazil. It has Mineral Resources of 276 million tonnes (Mt) at 38.33% Iron (Fe) and Ore Reserves of 196 Mt at 39.34%. The Project consists of the mine, processing plant, wholly owned port and a 194km railway, all operated by PBA. A Pre Feasibility Study (“PFS”) was published in January 2023, which delivered a post-tax net present value of US$949 million at a discount rate of 10% and a post-tax internal rate of return of 34%, with an average annual life of mine EBITDA of US$235 million annually. In the PFS, after ramp-up, the planned yearly average production was forecast to be 5.3 Mtpa of Fe concentrate, consisting of 4.4 Mtpa at 65.4% Fe and 0.9 Mtpa at 62% Fe concentrate. Over the life of the mine, Amapá is forecast to deliver free on-board C1 Cash Costs of US$35.53 / dry metric tonne.
As of March 28th 2024, Cadence’s total investment in the Amapá Project had increased by approximately US$1.1 million to approximately US$13.2 million, and consequently, the equity stake in the project now stands at 33.6%.
For further information contact:
|
|
Cadence Minerals plc | +44 (0) 20 3582 6636 |
Andrew Suckling | |
Kiran Morzaria | |
WH Ireland Limited (NOMAD & Broker) | +44 (0) 20 7220 1666 |
James Joyce | |
Darshan Patel | |
Fortified Securities – Joint Broker | +44 (0) 20 3411 7773 |
Guy Wheatley | |
Brand Communications | +44 (0) 7976 431608 |
Public & Investor Relations | |
Alan Green |
Cadence Minerals #KDNC – Placing to raise £500,000 and Issue of Warrants to Advance the Amapa Iron Ore Project
Cadence Minerals (AIM: KDNC; OTC: KDNCY) announces that it has successfully raised, subject to Admission, £500,000 before expenses (the “Fundraise”) through the placing of 16,666,667 new ordinary shares (the “New Ordinary Shares”) in the capital of the Company at a price of 3 pence per Ordinary Share (the “Issue Price”) and the issue of warrants to the subscriber of the New Ordinary Shares in the ratio of one warrant to each one New Ordinary Share subscribed for (the “Warrant”). The Fundraise was with a single institutional investor.
The Issue Price represents a discount of approximately 43 per cent. to the closing price of 5.25 pence per ordinary share on 4 April 2024, being the latest practicable business day prior to the publication of this Announcement.
The Warrants in the Fundraise grant rights to subscribe for one additional Ordinary Share for each Warrant held in the ratio of one Warrant for every one New Ordinary Share issued to the investor. The Warrants are exercisable at a price of 5 pence per Ordinary Share and expire on 31 March 2025.
The net proceeds of the Fundraise will solely be used to fund Cadence’s investment in the Amapá Iron Ore Project in Brazil (“Amapá”, “Project” or “Amapá Project”), specifically:
- Prepare a revised mine schedule, up to a Pre-Feasibility Study (“PFS”) level, to reflect an increased production of 5.5 million tonnes per annum (“Mtpa”), with 4.51 Mtpa at 65% Fe and 0.99 Mtpa at 62% Fe.
- Prepare and publish a revised PFS economic model that reflects the production increase and the 33% lower plant capital expenditure, which we announced on March 22, 2024.
- The sampling and testing of the 67% Fe “Green Iron” product flow sheet, to a PFS level or accuracy.
- If the testing of the “Green Iron” flow sheet is successful, the preparation and publication of a revised PFS economic model to reflect the higher product quality increased production.
- Working capital at the Amapá Project to fund ongoing licensing requirements, with the expectation that all the required licensing for construction will be granted by the end of 2024.
Application will be made for the admission to trading on the AIM market (“AIM”) of London Stock Exchange plc (“LSE”) for the New Ordinary Shares (“Admission”). Admission is expected to occur at 8.00 a.m. on or around 11 April 2024. The New Ordinary Shares will represent approximately 8.4 per cent. of the Company’s issued share capital immediately following Admission.
Following Admission, the Company’s issued and fully paid share capital will consist of 197,637,704 Ordinary Shares, all of which carry one voting right per share. The Company does not hold any Ordinary Shares in treasury. The figure of 197,637,704 Ordinary Shares may be used by shareholders as the denominator for the calculation by which they will determine if they are required to notify their interest in, or a change to their interest in, the share capital of the Company under the Disclosure Guidance and Transparency Rules of the Financial Conduct Authority.
The New Ordinary Shares will be issued fully paid and will rank pari passu in all respects with the Company’s existing Ordinary Shares.
Cadence CEO Kiran Morzaria commented: “I am pleased that we have been able to raise this money from a single investor at a pivotal time for the development and evolution of Amapá. This will enable completion of the revised PFS and fund the licensing process through to a license for construction at the end of 2024. I look forward to reporting back with further updates.”
For further information contact:
|
|
Cadence Minerals plc | +44 (0) 20 3582 6636 |
Andrew Suckling | |
Kiran Morzaria | |
WH Ireland Limited (NOMAD & Broker) | +44 (0) 20 7220 1666 |
James Joyce | |
Darshan Patel | |
Fortified Securities – Joint Broker | +44 (0) 20 3411 7773 |
Guy Wheatley | |
Brand Communications | +44 (0) 7976 431608 |
Public & Investor Relations | |
Alan Green |
Cadence Minerals #KDNC CEO Kiran Morzaria talks to StockBox Media
Stockbox Media interview with Cadence CEO Kiran Morzaria, where he discusses the successful cost savings & increased production at Amapá Iron Ore Project
Cadence Minerals #KDNC – Update on the Cadence Amapá Project investment and Equity Stake
Cadence Minerals (AIM: KDNC; OTC: KDNCY) is pleased to announce details of its increased equity stake in the Amapa Iron Ore Project (“Amapá”, “Project” or “Amapá Project”). The Amapá Project is an integrated iron ore project in the Amapá State of Brazil, with Mineral Resources of 276 million tonnes (Mt) at 38.33% Iron (Fe) and Ore Reserves of 196 Mt at 39.34% Fe.
The Amapá PFS delivered a post-tax net present value of US$949 million at a 10% discount rate and a post-tax internal rate of return of 34%, with an average annual life of mine EBITDA of US$235 million. With the planned production of 5.3 Mtpa of Fe concentrate, the Project is forecast to deliver free on-board C1 Cash Costs of US$35.53 per dry metric tonne.
The Project is about to undergo an amended economic assessment at a PFS level based on the positive results from the optimisation studies released earlier this month. This study will include lower capital expenditure, higher production rate and a possible reduction in mining costs.
Moreover, the Project is fully committed to advancing the development of the 67% Fe product flow sheet, as previously outlined in the announcement on 7 March 2024. It is anticipated to be at a production rate of 5.5 Mtpa.
Cadence Interest in the Amapá Project
At the end of September 2023, Cadence’s total investment in the Amapá Project stood at approximately US$12.1 million, with the equity stake in the project standing at 32.6%. As of March 28th 2024, Cadence’s total investment in the Amapá Project had increased by approximately US$1.1 million to a total investment of approximately US$13.2 million, and consequently the equity stake in the project now stands at 33.6%.
Cadence CEO Kiran Morzaria commented: “As our involvement and commitment to the Amapá Project increases, we’re ever more excited and enthused by the potential and promise that the newly recommissioned mine and infrastructure is set to deliver. With robust Mineral Resources and Ore Reserves, coupled with solid financial projections, we stand poised to unlock substantial value, and our increased equity stake reflects our confidence in the Project’s potential.”
“The forthcoming economic assessment builds upon our recent optimisation efforts, underscoring our commitment to maximising the project’s delivery potential wherever possible. Moreover, our commitment to advancing the 67% Fe product flow sheet underscores our proactive approach to meet evolving market demands in green steel.”
For further information contact:
|
|
Cadence Minerals plc | +44 (0) 20 3582 6636 |
Andrew Suckling | |
Kiran Morzaria | |
WH Ireland Limited (NOMAD & Broker) | +44 (0) 20 7220 1666 |
James Joyce | |
Darshan Patel | |
Fortified Securities – Joint Broker | +44 (0) 20 3411 7773 |
Guy Wheatley | |
Brand Communications | +44 (0) 7976 431608 |
Public & Investor Relations | |
Alan Green |
Cadence Minerals #KDNC – Optimisation Study Delivers Material Capital Savings at the Amapá Iron Ore Project
Cadence Minerals (AIM/NEX: KDNC; OTC: KDNCY) is pleased to report the successful completion of its capital expenditure optimisation program at the Amapá Iron Ore Project (the “Project”, “Amapa” or “Amapá Project”). The program has identified significant savings in processing plant recommissioning and increased production. The optimisation study was conducted at a pre-feasibility level and marks an important milestone in the company’s progress towards achieving cost-efficient and sustainable operations.
Highlights:
- PFS-level optimisation studies (the “Study”) have identified 33% (US$63.2 million) of capital savings associated with the beneficiation plant at the Amapá Project.
- The Study has resulted in a forecast increase in production of approximately 4.8% to 5.5 Mtpa of iron ore concentrate, of which 4.51 will be a 65% product and 0.99 Mtpa a 62% product.
- Alongside our joint venture partners, we plan to redesign the mine plan to reduce mining costs.
- The revised capex and mine plan will form the basis of an amended economic assessment at a PFS level.
- Fully committed to advancing the development of a 67% “Green Iron” Fe product flow sheet at a production rate of 5.5 Mtpa.
- The capital requirement for the entire Project is now in the bottom quartile of comparables at US$58 per million tonnes of annual capacity.
- The Study was completed ahead of schedule, so we do not anticipate any delays to the timeline already announced.
Cadence CEO Kiran Morzaria commented: “We’re thrilled to announce the successful completion of our capital expenditure optimisation program at the Amapá Iron Ore Project. This effort has delivered a substantial 33% reduction in capital costs, saving $63.2 million and forecasted a 4.8% to 5.5 Mtpa increase in iron ore concentrate production.
Moreover, given the Study was completed ahead of schedule, we do not anticipate any delays to the timeline already announced, even with the additional work associated with optimising the mine plan to accommodate the increased production.
We remain fully committed to advancing the development of the 67% Fe product flow sheet, aligning with our vision for sustainable growth and value maximisation.”
Background to Optimisations Studies
As per the announcement made on 7 March 2024, our joint venture company Pedra and Branca Alliance (“PBA”), which owns 100% of the Amapá Iron Ore project, engaged an engineering firm in 2023 to carry out an in-depth review of the processing plant flowsheet to significantly reduce capital and operating expenditures and, possibly, improving the iron ore concentrate quality.
We are pleased to report that the review of capital and operating expenditures is complete, and the 67% flow sheet development continues.
Results from Amapá Project Optimisation Studies
This part of the optimisation study focused on the iron ore beneficiation plant at the Amapá Project. It aimed to reduce the capital and operational expenditure while producing a product mix of 65% Blast Furnace Pellet Feed (“BFPF”) and 58% spiral concentrate.
An independent Chinese consulting engineering company carried out this work and identified several material capital savings, particularly in the equipment and materials suppliers. As a result of their work, the direct and indirect capital associated with the beneficiation plant has been reduced by US$63.2 million (approximately 33%) from US$191.7 million to US$128.5 million. Utilising the comparables within the PFS report published in 2023, the entire capital required for the Amapá Project is in the bottom quartile of capital intensity at US$58 per million tonnes of capacity; the median of the comparable projects is US$142 per million tonnes of capacity.
In addition, the utilisation and availability rates of the beneficiation plant were increased, resulting in an increase in plant throughput and production from 5.28 million tonnes per annum (“Mtpa”) to 5.5 Mtpa, both on a dry basis. This also led to a marginal reduction in operating costs. Out of the 5.5 Mtpa, approximately 4.51 Mtpa will be 65% BFPF, and 0.99 Mtpa will be a 58% spiral concentrate.
Next Steps
Based on the positive results derived from the optimisation study, which included an increase in throughput, we have decided, in conjunction with our joint venture partners, to redesign the mine plan to reduce mining costs. As already highlighted, the Study was completed ahead of schedule. Therefore, we do not anticipate any delays in the already announced timeline.
This revision and the revised capex will form the basis of an amended economic assessment of the Project at a PFS level. Additionally, we are fully committed to advancing the development of the 67% Fe product flow sheet, as previously outlined in the announcement on 7 March 2024. We also anticipate it being at a production rate of 5.5 Mtpa.
About the Amapá Project and Cadence’s Ownership
The Amapá Project is a brownfield integrated iron ore project in the Amapá State of Brazil. It has Mineral Resources of 276 million tonnes (Mt) at 38.33% Iron (Fe) and Ore Reserves of 196 Mt at 39.34%. The Project consists of the mine, processing plant, wholly owned port and a 194km railway, all operated by PBA. A PFS was published in January 2023. The PFS delivered a post-tax net present value of US$949 million at a discount rate of 10% and a post-tax internal rate of return of 34%, with an average annual life of mine EBITDA of US$235 million annually. In the PFS, after ramp-up, the planned yearly average production was forecast to be 5.3 Mtpa of Fe concentrate, consisting of 4.4 Mtpa at 65.4% Fe and 0.9 Mtpa at 62% Fe concentrate. Over the life of the mine, The Project is forecast to deliver free on-board C1 Cash Costs of US$35.53 / dry metric tonne.
At the end of September 2023, Cadence’s total investment in the Amapá Project stood at approximately US$12.1 million, with the equity stake in the Project standing at 32.6%. Since then, Cadence has continued to invest in the Amapá Project, and a further updated equity position will be provided at the end of March 2024.
For further information contact:
|
|
Cadence Minerals plc | +44 (0) 20 3582 6636 |
Andrew Suckling | |
Kiran Morzaria | |
WH Ireland Limited (NOMAD & Broker) | +44 (0) 20 7220 1666 |
James Joyce | |
Darshan Patel | |
Fortified Securities – Joint Broker | +44 (0) 20 3411 7773 |
Guy Wheatley | |
Brand Communications | +44 (0) 7976 431608 |
Public & Investor Relations | |
Alan Green |