Cadence CEO Kiran Morzaria talks to Mark Fairbairn at Stockbox and covers the latest update re the timelines for obtaining essential licenses for the Amapa iron ore project in Brazil. Kiran explains how the timelines have been significantly shortened 12 to 16 months, a marked improvement from the typical 36-month process. Following the installation license approval, the project’s construction is expected to span 12 to 18 months, potentially allowing production to resume within approximately two and a half to three years.