Blencowe Resources #BRES – Major Milestone as Blencowe Delivers Substantial Pre-Feasibility Study for Orom-Cross Graphite Project

Highlights

  • Pre-Feasibility Study (PFS) completed on time and under budget.
  • PFS indicates a robust, long-term, profitable graphite mining operation at Orom-Cross.
  • Highlights include:
    • Initial life of mine 14 years which can be further incremented by additional drilling.
    • Net Present Value (post-tax) of US$496M / IRR (post-tax) of 50%.
    • Operating cost (FOB Mombasa port) of US$499/t, underlining Orom-Cross as one of the lowest cost graphite projects worldwide.
    • Valuable basket of end-products delivering a significant weighted average selling price of US$1,307/t, thereby ensuring a considerable operating margin per tonne.
    • US$1.398 billion EBITDA delivered from project over life of mine, with an average US$100M EBITDA per annum for 14 years.
    • US$1.10 billion cumulative Net Cash delivered from project over life of mine.
    • Initial Capital requirement of US$62M, inclusive of contingency, which is lower than previously reported capex (PEA 2021) by 23%.
    • Production to commence at rate to deliver ~36,000tpa end-products as 96-97% LOI concentrates in year 1, ramping up in stages thereafter to ~150,000tpa by year 10.
    • ~50% of end-product in higher value +100 to +50 mesh fractions.
    • Blencowe to apply for Free Trade Zone License (FTZL) in 2H 2022 which in turn will bring considerable advantages, including 10-year corporate tax exemption.
  • PFS signed off by leading graphite technical experts Battery Limits Pty Limited (Australia), who have delivered several other leading graphite project feasibility studies in the past.
  • Flake graphite forecast to move into significant supply deficit medium term as increased demand for electric vehicles (EVs) lifts demand for lithium-ion batteries.  Graphite is a non-replaceable input material into lithium-ion batteries.
  • Blencowe will now move towards Initial Stage production at Orom-Cross by mid-2023.

Blencowe Resources (“Blencowe” or the “Company”) (LSE: BRES) is pleased to announce results of the Pre-Feasibility Study it has been conducting at its flagship Orom-Cross Graphite Project in Uganda.  These results highlight an exceptional long-life project that delivers considerable returns over an initial life of mine period of fourteen years.  In addition, the PFS indicates an initial capital requirement that has been lowered by 23% since the Preliminary Economic Assessment (“PEA”) announced in 2021.

The PFS has been delivered in conjunction with leading graphite technical expert Battery Limits Pty Ltd (“Battery Limits”) who have signed off on several other leading graphite project feasibility studies worldwide. 

Executive Chairman of Blencowe, Cameron Pearce commented:

“This PFS represents our first major milestone for Orom-Cross and the results are outstanding.  We have considerably outperformed the Preliminary Economic Assessment that we delivered in 2021 in all key areas and yet we have done this with an initial capital requirement that is now significantly lower than that shown within the PEA.” 

He added “The Orom-Cross NPV (Net Present Value) of US$496M is excellent, especially in relation to this lower capex, and proves that this graphite project is a standout.  It already has a long mine life that can be extended at any time with additional drilling and it delivers a high quality concentrate with specific element content that is unique and which will elevate demand for all of the end-products we sell.  Selling graphite is one of the key challenges for a successful operation so this is critical. 

As a result of 50% of these end-products being larger flake size categories Orom-Cross has a substantial weighted average selling price for its basket of end-products, yet it also has one of the lowest total operating costs of any graphite project worldwide.  This ensures considerable operating margins over life of mine, which in turn will deliver over US$1 billion free cash to Blencowe as return on investment. 

Various other graphite projects have indicated much larger start-up production tonnages than we have, which in some cases fabricate higher numbers for their project NPVs, but we do not believe that over-inflated early sales volumes are deliverable; as such we have adopted a more conservative profile for both start-up and the ramp-up thereafter.  Credibility is very important to us.  This helps delivers a lower initial capital requirement for Blencowe to commission the mine which is another big advantage.

Together all of these above are tremendous results for our Project and we will now begin focussing on bringing Orom-Cross to an initial stage production during 2H 2023 as our next significant milestone.”

Orom-Cross Graphite Project: Pre-Feasibility Study

The following areas highlight the quality of the project, and provide the basis for Blencowe to move towards Initial Stage production within the next 12-18 months.  Main production is targeted for 2025.

Key Performance Indicator

 

  Comment
Life of Mine 14 years Can extend at any stage with further drilling
Average tonnes mined pa 1.6Mtpa Start-up 400ktpa, moving to 2.4Mtpa at year 7
Average tonnes (concentrate) produced pa over life of mine 101,000tpa Start-up 36ktpa; moving to 150ktpa by year 7

1.42M tonnes over life of mine

Initial Capital Requirement US$62M Plant, camp, equipment, all infrastructure, plus working capital & contingency
Net Present Value (NPV) US$496M 10X return on capital invested
Internal Rate of Return (IRR) 50% Highlights strong rate of return on investment
Weighted Average Selling Price/t – life of mine US$1,307/t 5 different end-products produced, with ~50% in the higher value +100 to +50 mesh fraction sizes
Operating Cost (FOB Mombasa port) – average life of mine US$499/t C2 costs, including mining, processing, admin, manpower, logistics, sales and marketing costs
Average EBITDA per annum – life of mine US$100M US$1.398Bn total EBITDA earned over life of mine
Free Cash Generated US$1.10Bn Net Cash (after tax and royalties) delivered to Company over life of mine
  1. Mining and Processing

Orom-Cross has an existing JORC Standard Resource of 24.5Mt at 6.0% presenting from surface, which provides for a shallow, low cost, open pit mining operation.  All mining within this first 14 years will be done from 0-25m depth.  Approximately 500,000 tonnes of ore will be mined per annum from commissioning date and this will increase to 2.4Mtpa by the time the project is fully ramped up in year 10.  The existing JORC Resource provides an initial mine life of 14 years and further resources, higher production volumes and an extended mine life can all be obtained at any stage via drilling additional ready-targets.   This is however not considered a priority at the moment.

Mining will be free-dig with no drill and blast requirement.  Initial ore will come from saprolite (clay) but is expected to move into fresh around 15-20m depth on average.  Both of the deposits identified in the drilling programmes (Northern Syncline and Camp Lode) will be mined and a composite blend of both will be input into the processing plant that will be constructed on-site.

An initial 35,000tpa of end-product as concentrates will be delivered from the plant which increments in two additional stages to 150,000tpa once the mine is fully ramped up.  Considerable metallurgical test work has been done on the end-products to determine their chemistry and characteristics and this shows that Orom-Cross can deliver a high quality >96% LOI concentrate that is unique in several key aspects (as highlighted in the June 2022 announcement on final met test results).  Circa 35% of these end-products will be coarse flakes and ~50% will be in the +100 to +50 mesh higher value categories.  The remaining smaller flake products can be sold into the fast-emerging battery market, which is forecast to grow considerably over the long term thus providing a channel for incremental growth and sales.

  1. Capital Requirement

Blencowe will commence main operations from 2025 at an initial output of 35,000tpa end-product, which is considerably lower than the initial start-up volume as per the PEA (2021).

This is due to guidance from Blencowe’s experienced graphite sales and marketing advisors targeting a more conservative ramp up profile to ensure all products are able to be sold on start-up into various markets as identified.  It is likely that various different products will be sold into all of the key graphite markets, including engineered products, thermal management and energy storage.

Pre-qualification of all end-products will commence from initial stage smaller scale production facility at Orom-Cross from 2023, which will deliver bulk samples over a period of 12-24 months prior to the main plant being commissioned, in order to build relationships with end-users over that period.  This will ensure that all end-products are qualified and can be locked into binding sales agreements once main stage production commences in 2025.

This lower volume start-up position has resulted in a reduced initial capital requirement of US$62M (down by 30% from the USD80M capex as per the PEA in 2021).

Capital Item US$ M %
Processing Plant 27.3 44.0
EPCM 5.3 8.5
Other Indirect Costs 3.1 5.0
Plant Infrastructure, including Tailings Storage Facility (TSF) 8.1 13.1
Camp and Facilities 8.3 13.4
Mining Capital, Workshops, Vehicles 2.6 4.2
Owners Costs 2.4 3.9
Contingency 4.9 8.0
 

TOTAL

 

62.0

 

100%

This requirement is expected to be funded by a combination of both debt and equity via strategic investors and funding partners.  The full capital requirement for each of the three stages is indicated in the table below.

Stage Year Capital Requirement

US$ M

Use of Funds
1 2024/5 62 Initial 800,000tpa plant

All infrastructure, including power, roads, TSF, communications and mine camp.

Includes start-up costs and working capital

2 2027/8 48 Additional 800,000tpa plant capacity, plus all associated infrastructure
3 2029/30 47 Additional 800,000tpa plant capacity, plus all associated infrastructure
  1. Infrastructure

Orom-Cross benefits by considerable key infrastructure already in place, which in turn lowers the capital required to commission the mine.  There are existing tarred roads from the regional centre Kitgum (90kms from site) all the way through to Mombasa port in neighbouring Kenya, and the road from Kitgum to nearby Orom (10kms from site) will be tarred by 2025; work on that is already underway.  Blencowe will establish local roads required around the mine site.

Power will be connected to the national grid which is currently nearby at Orom and will provide lower cost, energy-efficient hydro-power, and either solar or diesel generators will be used as backup.  Wireless communications will be connected on site giving all range of phone and internet options.  There is plentiful water on and around the site and bores will be sunk for clean water.

A smaller processing facility and mine camp will be set up for initial stage production from 2023 to deliver bulk samples for pre-qualification, and a larger camp will be constructed together with additional plant, storage, admin offices and a larger tailings facility, prior to 2025 main start-up.

  1. Operating Costs

Orom-Cross benefits from several key attributes that combine to deliver one of the lowest operating cost graphite projects worldwide.

Specifically these include:

  • Low strip ratio for open pit mining (graphite presents from 0-25m below surface)
  • No drill and blast required and minimal crushing (no hard rock)
  • Lower energy costs (low cost hydro power off the national grid)
  • Lower labour costs; and
  • A simple process flow through a standard floatation plant.
Cost Centre

 

Average Cost per tonne (USD/t) % Total
Mining 90 18.0
Processing 180 36.1
Fuel 3 0.6
Project Personnel 48 9.6
Project Services 35 7.0
Depreciation 18 3.6
Transport & Logistics 110 22.0
Sales & Marketing 15 3.1
 

TOTAL

 

499/t FOB port

 

100%

Mining will be owner-operated using equipment either purchased outright or leased.  Training will be given to locals to fill positions wherever possible and Blencowe intends to build a strong base of experienced in-country personnel for all positions over life of mine.

Ore will be mined from both the Northern Syncline and Camp Lode deposits and stockpiled for processing through the plant, which will be located on-site and near to the mining operations.  An initial 500,000tpa of ore will be throughput but this will expand to 2.4mtpa over a series of ramp ups during the first ten years’ life of mine.  This will result in 35,000tpa of end-products delivered as concentrates from year 1 that will expand to 150,000tpa by year 10.  Operating costs per tonne will reduce over the life of mine as the production tonnage ramps up.

The processing flowsheet consists of a flash and rougher flotation stage followed by a primary cleaning circuit with a polishing mill, followed by three stages of cleaner flotation. The intermediate concentrate is classified and then further upgraded in secondary cleaning circuits with stirred media mills (SMM) followed by cleaner flotation.

Orom-Cross will deliver at least five different end-products, characterised by different mesh size fractions; namely +50 mesh, + 80 mesh, +100 mesh, +150 mesh and -100 mesh.  These products will all have different markets and will be branded and packaged at site.  Blencowe intends to apply for a Ugandan Free Trade Zone License (FTZL) in 2H 2022 which will allow for all goods for export to be custom-cleared at the mine site before being transported to Mombasa port by truck for shipment to end-users.

Initially the transport to port will be done via road but it is expected that by 2025 main plant start-up there may be a rail option available nearby which would lower logistics costs further.  Orom-Cross will be able to utilise cheaper backfill options for road transport as both Uganda and South Sudan are land-locked countries and therefore require substantial volumes of imported goods delivered by trucks, which often return to Mombasa port empty.  This is a key advantage.

  1. Weighted Average Selling Price

The basket of end-products that Orom-Cross produces will deliver a strong weighted average sales price of ~US$1,307/t.  Prices have been determined using updated Lone Star Tech Minerals (leading graphite sales and marketing expert) graphite pricing data, with forecast increments through to proposed 2025 start for the main production facility.

The weighted average selling price is made up as follows:

Flake Size Mesh Size 96-97% LOI

2025

%

End Product

Weighted Average US$/t
Jumbo +32 3,510 1.5 53
Jumbo +50 2,830 12.2 345
Large +80 1,474 22.5 332
Large +100 1,091 10.6 116
Medium +150 990 15.1 149
Small -100 / -200 982 / 752 11.9/26.0 117/196
        1,307

The table shows a wide range of price differentiation between coarse and fine flake sizes for 96-97% LOI (loss on ignition) concentrates, and both current prices as well as forecast prices for 2025 expected start-up date.  Orom-Cross benefits from having ~35% of its end-products as jumbo or large flake sizes (+80 mesh) as these products sell into markets at a considerable premium to the smaller flake/mesh sizes.  The concentrates also benefit from having very low impurities.

Strong anticipated future demand for smaller flake product that can be upgraded to 99.9% SPG and used within batteries for EVs presents growth potential for further demand ahead, with this forecast to positively impact prices considerably over the next decade and beyond.  The market has already seen an upward shift in the price of these mesh sizes during 2022.

  1. Sales and Marketing

Blencowe has been working closely with experienced graphite marketing consultant Lone Star Tech Minerals LLC (USA) during the PFS period to identify products and markets to sell its graphite products into ahead.  Lone Star have over 30 years’ direct experience in graphite sales and their expertise has been valuable in all facets, including metallurgical test work, identifying product specifications, branding, packaging, customer identification, interaction and liaison.  Blencowe will continue to work with Lone Star as Orom-Cross moves towards first production.

Blencowe’s marketing strategy will be to construct a smaller scale initial plant at Orom-Cross from 2023 that will deliver ~1,500tpa of end-products as concentrates for bulk sample sales into end-users.  This process of pre-qualifying will continue in parallel to the main plant being constructed in 2024 for target 2025 start-up, with all products thereby having had 12-24 months’ history of sales into customers before more extensive production commences.

Blencowe intends to seek key ISO certifications for its plant and products through this pre-qualification period to ensure highest possible standards which will then be reflected in higher demand for its products, and potentially higher prices.

  1. Cash Flow

The high net operating margin generates substantial cash flow from Orom-Cross, particularly from when the mine has fully ramped up to 150,000tpa capacity by year 10.  This in turn generates free cash net of all taxes of US$1.10 billion from the Project over the initial 14 years’ life of mine.  As only ~1% of the full Orom-Cross graphite deposit will have been mined out by then it is very likely that further drilling will result in an considerable extension to the life of mine well beyond the initial 14 years, and with that significant additional net cash flow.

Royalties of 5% have been added and a 10-year exemption from corporate tax is also included in the model.  Thereafter a standard rate of 30% corporate tax is used.  Whilst Blencowe will not apply for any tax exemption until the Definitive Feasibility Study is completed the Company has been made aware the investment quantum for Orom-Cross and the nature of the exported end-products, plus certain other features, will allow for such an exemption to likely be granted; as such it has been included within the modelling.

Provision has been made for payments to the local community as dictated by the existing Local Community Agreement already in place, and for other means for Blencowe to assist such as water bores, health and educational support and various minor infrastructure.

  1. Management and staffing

Blencowe will ensure operational delivery of end-product via experienced management at Orom-Cross, specifically in key areas such as the processing plant.  However the Company will focus on training local staff wherever possible to transfer skills and to ensure participation. Ultimately the full operation will have >400 persons employed, operating in shifts to ensure constant mining and processing all year round.  Mining is will be owner-operated using dry hire equipment, as opposed to contract mining.

  1. ESG (Environmental, Social & Governance)

Blencowe is taking a firm stance from the outset on life cycle sustainability at Orom-Cross with every effort made to ensure the project operates using renewable energy sources wherever possible, and any non-renewable options are only considered as emergency or backup where no other alternative is possible.

Orom-Cross benefits from the ability to utilise hydro-electric power sourced from the Ugandan national grid and various solar options are under consideration and will be examined further within the Definitive Feasibility Study stage.

Social programmes are already in place to ensure the local community benefits from a successful mining operation, and Blencowe will continue to work closely with the local community ahead to ensure its continued support.  Strong governance and risk management are critical to the success of the Project and Blencowe will monitor these aspects at all times to international standards.

  1. Strategy Forward and Timing

Blencowe is committed to bringing Orom-Cross into first production as soon as practically possible.  Subject to further revisions due to prevailing circumstances the following strategy and associated timings reflect the Company’s plan to advance Orom-Cross over the medium term:

Milestones

 

Dates Comments
Stage 1 (pilot plant) feasibility study 3Q 2022 Specific study for 1,500tpa plant for bulk sample sales to end-users from 2H 2023 onwards
Stage 1 plant implementation 1H 2023 Processing plant and associated infrastructure for initial stage production
Stage 1 plant commissioning 2H 2023 Commencement of operations at Orom-Cross

 

Definitive Feasibility Study 2023 DFS on main plant in parallel with development of Stage 1 main plant and infrastructure
Decision to Mine (main plant)

 

End-2023 Completion of DFS and decision to raise necessary funds for main plant implementation
Funding & implementation (main plant) 2024 Construction of main plant on-site
Main plant commissioning

 

2025 Commencement of operations (main plant)

As highlighted above, Blencowe anticipates moving into initial stage production at Orom-Cross during 2023 and building relationships with end-users via delivery of bulk samples sold over a period thereafter whilst the Company completes the DFS and builds the main production facility.

  1. Graphite demand within World Markets

Graphite is used in many different applications and there will be a different demand profile ahead for each based on prevailing circumstances, and as these products are in different sectors of the market they do not necessarily impact one another.  Blencowe will be looking to sell end-products into each of these market segments below:

  • Engineered Products

Electronics, agriculture, automotive, lubricants, ceramics, government defence, carbon brush and foils products that use natural flake graphite products.  Other example applications that use graphite powder additives include friction, powder metallurgy, ceramics, foils, fire retardants, pencil, lubricants, dispersions, and carbon brush.

  • Thermal Management

Applications that require graphite powder in various mesh or micron sizes as a thermal insulator or conductor in a wide range of applications including traditional and advanced graphite products for high end refractories, standard refractories, HMF (Hot Metal Forging), HMT (Hot Metal Toppings), crucibles, foundry and geothermal.

  • Energy Storage

The energy sector continues to require new producers of consistent and high quality advanced carbon and graphite products to meet the needs of the global population for consumer goods, grid stabilisation, transportation, communications, aerospace and medical device advances. Applications and markets within the energy storage group will experience increased demand for innovative high tech graphite solutions.

The applications that are receiving the least attention requiring significant volumes of high purity micronised carbon powders are secondary battery (cathode) and primary battery (alkaline); both of which use high purity (99.9% LOI MIN) micronised carbon or graphite powder as a conductive additive without the need for any additional morphology modification.

There is significant discussion on the current and future needs of advanced battery technologies for critical raw material supply; specifically lithium, carbon and graphite products. Advances in battery and raw material technologies require increasing higher quality in advanced carbon or graphite products. These advances need to meet not only energy density requirements, but power density and energy requirements as industrial and consumer electronics become more sophisticated. Blencowe is making strategic steps to meet those future challenges. Electrochemistry applications that use carbon or graphite powders as a conductive additive include batteries, fuel cells, & super-capacitors.

Price points for each market group are not the same for every application and can vary significantly from one to another.  A traditional or advanced graphite powder production facility must possess the capability to produce multiple products created from a single source or feedstock with processes and packaging to meet specific customer requirements. This will encompass serving multiple product families with various combinations resulting in large number of unique permutations. Specific target applications have the potential to deliver significant incremental revenue and profits creating long term sustainability and future growth for the Company.

An advanced carbon powder manufacturing program will include certifications to include ISO: 9001 (QA/QC) and ISO: 14001 (EMS) in line with industry, application and customer requirements.  Blencowe Resource’s Orom-Cross graphite project is set to be part of the next generation of traditional and innovative advanced carbon powder products for the global market. It is prudent in any graphite business strategy to diversify product offerings and target market focus to provide for progressive revenue streams to weather a variety of market dynamics that could potentially affect one market or another.

Due to graphite’s metallurgical rarity, its unique physical and chemical properties, and its growing importance in high technology applications and green energy initiatives, natural graphite has been declared a strategic mineral by both the USA and European Union (EU).  Natural Graphite is positioned as one of 24 critical raw materials out of 54 candidate materials.

The critical success factor for Blencowe Resources will be the Company’s manufacturing focus on delivering higher quality, consistent flake graphite products and not focusing solely on selling bulk tonnes of lower quality flake graphite at lower prices; a strategic position of quality over quantity.

For further information please contact:

  Blencowe Resources Plc

Sam Quinn

www.blencoweresourcesplc.com

Tel: +44 (0)1624 681 250

info@blencoweresourcesplc.com

 

Investor Relations

Sasha Sethi

Tel: +44 (0) 7891 677 441

sasha@flowcomms.com

 

Tavira Securities

Jonathan Evans

Tel: +44 (0)20 7100 5100

jonathan.evans@tavirasecurities.com

 

First Equity Limited

Jason Robertson

Tel: +44(0)20 7330 1833

jasonrobertson@firstequitylimited.com

 

Twitter https://twitter.com/BlencoweRes

LinkedIn https://www.linkedin.com/company/72382491/admin/

 

 

Background

Orom-Cross Graphite Project

Orom-Cross is a potential world class graphite project both by size and end-product quality, with a high component of more valuable larger coarse flakes within the deposit. A 21-year Mining Licence for the project was issued by the Ugandan Government in 2019 following extensive historical work on the deposit and Blencowe is now in the Feasibility Study phase as it drives towards first production targeted for 2023.

Orom-Cross presents as a large, shallow open-pitable deposit, with a maiden JORC Indicated & Inferred Mineral Resource deposit of 24.5Mt @ 6.0% Total Graphite Content. Development of the resource is expected to benefit from a low strip ratio and free dig operations, thereby ensuring lower operating and capital costs.

Akelikongo Nickel Project

Akelikongo is a highly prospective nickel sulphide exploration project that has previously had considerable work completed by Rio Tinto and Sipa to establish three mineralised lenses to date.  It represents an opportunity for Blencowe to add further value through a targeted work programme that will seek to delineate higher grade and thicker intercepts of nickel.

Nickel sulphide deposits are rare and valuable and the prospect of further exploration success gives Blencowe suitable incentive to develop this asset under a structured earn-in agreement, whereby 100% of the asset can ultimately be acquired for US$1.5m, 100% payable in shares.


Leave a comment

I would like to receive Brand Communications updates and news...
Free Stock Updates & News
I agree to have my personal information transfered to MailChimp ( more information )
Join over 3.000 visitors who are receiving our newsletter and learn how to optimize your blog for search engines, find free traffic, and monetize your website.
We hate spam. Your email address will not be sold or shared with anyone else.